Followings are some of the statements related to drop spillway:
Choose the correct answer from the options given below:
ड्रॉप स्पिलवे (Drop spillway) से संबंधित निम्नलिखित कथनों पर विचार कीजिए:
नीचे दिए गए विकल्पों में से सही उत्तर चुनें:
Components and design functions of straight drop spillways:
Statement (B) is correct: Transverse sills (end sills) placed across the stilling basin floor stabilize and force the formation of a hydraulic jump within the basin, effectively dissipating kinetic energy.
Statement (C) is correct: Longitudinal sills running parallel to the direction of flow prevent cross-currents and eddies, guiding and straightening discharge uniformly downstream.
Statement (A) is incorrect: Standard SCS criteria require straight reaches of typically 15 to 30 meters (not a rigid 50 m requirement).
Statement (D) is incorrect: Cutoff walls are designed to reduce (not increase!) seepage uplift pressure and eliminate piping failures beneath the structure.
ड्रॉप स्पिलवे (Drop spillway) के घटक:
कथन (B) सही है: अनुप्रस्थ सिल (Transverse/End sill) स्थिर बेसिन में हाइड्रोलिक जंप बनाकर गतिज ऊर्जा का ह्रास करती है।
कथन (C) सही है: अनुदैर्ध्य सिल (Longitudinal sill) प्रवाह को सीधा बनाए रखने और भंवरों को रोकने में मदद करती है।
कटऑफ दीवार का उद्देश्य अपलिफ्ट दबाव को कम करना होता है (बढ़ाना नहीं)।