2
ICAR JRF Irrigation & Drainage Engineering Irrigation And Drainage Engineering 29 Jun 2024Shift 1
MCQ (Single Correct) +4 −1
Awater harvesting structure has an expected life of 10 years and is designed for flood magnitude of return period of 20 years. What is the risk of hydrologic design?
  • Hydrologic Risk of Failure for Hydraulic Structures:
  • Risk Formula:
$$R = 1 - (1 - P)^n = 1 - \left(1 - \frac{1}{T}\right)^n$$

where:

  • $T = 20\text{ years}$ is the design return period $\implies P = \frac{1}{20} = 0.05$
  • $n = 10\text{ years}$ is the expected operational lifespan
  • Calculation:
$$R = 1 - (1 - 0.05)^{10} = 1 - (0.95)^{10}$$ $$(0.95)^{10} \approx 0.5987$$ $$R = 1 - 0.5987 = 0.4013 = 40.13\% \approx 40\%$$
  • Conclusion: Hydrologic risk is 40% (Option 1).

Correct option: (1) 40%

Explanation not matching this question? क्या व्याख्या इस प्रश्न से मेल नहीं खा रही? Report
Want to practice this paper in exam conditions? क्या आप परीक्षा जैसे माहौल में अभ्यास करना चाहते हैं? Test yourself in 5-question batch format with timer and hidden answers. 5-प्रश्नों के बैच फॉर्मैट, टाइमर और छिपे उत्तरों के साथ खुद को परखें।
Start Practice Mode → प्रैक्टिस टेस्ट मोड शुरू करें →

Irrigation & Drainage Engineering विषय एवं अध्याय

विषय एवं पाठ्यक्रम के अनुसार सभी अध्याय देखें

Official PYQ Papers

Previous Year Papers of Irrigation & Drainage Engineering

Practice official shift-wise question papers with answer keys and detailed explanations on the actual exam pattern.

1
Total Available Previous Papers

Choose Exam

Exam Directory

Browse official Previous papers and mock tests

11 Major Agriculture Exams Available