6
ICAR JRF Irrigation And Drainage Engineering 29 Jun 2024Shift 1
Match the Following +4 −1
Match List with List. \(Characteristics) method)

Choose the correct answer from the options given below :

List - I
Baseflow Separation Method
List - II
Technique
A Straight line method Straight line method I Connects point of hydrograph rise directly to inflection point on recession limb Connects point of hydrograph rise directly to inflection point on recession limb
B Fixed base method Fixed base method II Extends surface runoff duration for fixed time interval 'N' days after peak Extends surface runoff duration for fixed time interval 'N' days after peak
C Variable slope method Variable slope method III Extends pre-storm recession curve under the hydrograph peak Extends pre-storm recession curve under the hydrograph peak
D Digital filter method Digital filter method IV Uses signal processing recursive algorithm to separate high and low frequency components Uses signal processing recursive algorithm to separate high and low frequency components

Irrigation & Drainage Engineering Subjects

Browse all chapters by subject

Official PYQ Papers

Previous Year Papers of Irrigation & Drainage Engineering

Practice official shift-wise question papers with answer keys and detailed explanations on the actual exam pattern.

1
Total Available Previous Papers

Choose Exam

Exam Directory

Browse official Previous papers and mock tests

10 Major Agriculture Exams Available