ICAR JRF Renewable Energy Engineering Renewable Energy Engineering 29 Jun 2024Shift 1
MCQ (Single Correct) +4 −1
When estimating the load for a PV system, which factor is not typically considered?
  • Electrical Load Estimation for Solar PV Systems:
  • Sizing electrical loads for a photovoltaic power system strictly requires:
  • Power rating of connected loads (watts) and daily duty cycle (hours/day) to compute total daily energy demand (watt-hours/day).
  • Peak Sun Hours (PSH) available at the installation site.
  • Overall system efficiency (including inverter, wiring, and charge controller losses).
  • Battery storage capacity and days of autonomy for stand-alone setups.
  • Wind Speed: An aerodynamic structural parameter for mechanical mounting design or wind turbine siting, but is not considered in electrical PV load estimation.
  • Conclusion: Wind speed (Option 4).

Correct option: (4) Wind speed

Explanation not matching this question? क्या व्याख्या इस प्रश्न से मेल नहीं खा रही? Report
Want to practice this paper in exam conditions? क्या आप परीक्षा जैसे माहौल में अभ्यास करना चाहते हैं? Test yourself in 5-question batch format with timer and hidden answers. 5-प्रश्नों के बैच फॉर्मैट, टाइमर और छिपे उत्तरों के साथ खुद को परखें।
Start Practice Mode → प्रैक्टिस टेस्ट मोड शुरू करें →

Renewable Energy Engineering Subjects

Browse all chapters by subject

Biochemical Conversion Technology

1 Topic
Official PYQ Papers

Previous Year Papers of Renewable Energy Engineering

Practice official shift-wise question papers with answer keys and detailed explanations on the actual exam pattern.

1
Total Available Previous Papers

Choose Exam

Exam Directory

Browse official Previous papers and mock tests

11 Major Agriculture Exams Available