Established by the Development Assistance Committee of the Organisation for Economic Co-operation and Development (OECD-DAC), the internationally accepted five core evaluation criteria for development projects are:
Relevance: Is the intervention doing the right things?
Effectiveness: Is the intervention achieving its stated objectives?
Efficiency: How well are resources being used?
Impact: What broader long-term difference does the project make?
Sustainability: Will the benefits last after funding ceases?
Conclusion: Option 1 represents the standard OECD-DAC five-criteria framework.
Properties of the Cobb-Douglas Production Function:
For $Y = A X_1^\alpha X_2^\beta$:
Output elasticities are directly given by parameters $\alpha$ and $\beta$.
Allows direct estimation via linear transformation ($\\ln Y = \ln A + \alpha \ln X_1 + \beta \ln X_2$), conserving degrees of freedom and simplifying multi-regressor estimation.
Isoquants are Strictly Downward Sloping (Negatively Sloped): Isoquants are convex to the origin with a negative marginal rate of technical substitution ($MRTS = -\frac{dX_2}{dX_1} = \frac{\alpha X_2}{\beta X_1} \gt 0$).
Therefore, the assertion that “Iso-quants of CD function are positively sloped” is untrue / false, making Option 2 the correct answer.
Explanation not matching this question?क्या व्याख्या इस प्रश्न से मेल नहीं खा रही?Report
Q.115
Agricultural Economics- ICAR JRF/SRF 2024
MCQ (Single Correct)
What does "Gantt chart” represent in project management?
Invented by American management consultant Henry Gantt in the 1910s, a Gantt Chart is a graphical bar chart that illustrates a project schedule and timeline showing individual project activities/tasks, their start and end dates, and their expected durations along a horizontal time axis.
It visually tracks planned versus actual milestone progress and identifies concurrent tasks.
Correct option: (2) A timeline that shows project tasks and their durations