The second nuclear power plant of Rajasthan is proposed at Danpur in Banswara district (Mahi Banswara Atomic Power Project).
- Project Details: The plant is being developed by NPCIL (Nuclear Power Corporation of India Ltd.) in joint venture with NTPC (ASHVINI), comprising 4 indigenous Pressurized Heavy Water Reactor (PHWR) units of 700 MWe each (total 2800 MW).
- Water Source: Water will be drawn from the Mahi Bajaj Sagar Dam reservoir.
- First Nuclear Plant: Rajasthan's first nuclear power station is RAPS (Rajasthan Atomic Power Station) at Rawatbhata (Chittorgarh), established with Canadian collaboration in 1973.
- Heavy Water Plant: Rawatbhata also hosts India's first commercial heavy water production plant.
राजस्थान का दूसरा परमाणु ऊर्जा संयंत्र बाँसवाड़ा जिले के 'दानपुर' में प्रस्तावित है (माही बाँसवाड़ा परमाणु विद्युत परियोजना)।
- परियोजना की क्षमता: न्यूक्लियर पावर कॉरपोरेशन ऑफ इंडिया (NPCIL) और NTPC के संयुक्त उपक्रम द्वारा यहाँ 700 मेगावाट की 4 स्वदेशी दाबित भारी जल रिएक्टर (PHWR) इकाइयां (कुल 2800 मेगावाट) स्थापित की जा रही हैं।
- जल आपूर्ति: इस संयंत्र को भारी मात्रा में शीतलन जल की आपूर्ति माही बजाज सागर बांध से की जाएगी।
- प्रथम परमाणु संयंत्र: राजस्थान का पहला परमाणु विद्युत गृह 'रावतभाटा' (चित्तौड़गढ़) में 1973 में कनाडा के सहयोग से स्थापित किया गया था (यह भारत का दूसरा परमाणु संयंत्र था)।
- भारी जल संयंत्र: रावतभाटा में भारी जल (D2O) संयंत्र भी संचालित है।